The necessity of project schedule updating monitoring statusing

Posted by / 05-Sep-2014 17:07

The necessity of project schedule updating monitoring statusing

Activity duration updates denotes the passage of time from the start date, not actual work accomplished on the activity Scheduling software will adjust the remaining duration in order to yield the entered percentage complete Estimating a percentage of work or time complete is an inexact science Activity managers and schedulers are accustomed to estimating remaining duration Subjectivity of percent complete estimates becomes more apparent the longer the activity’s duration Statusing progress entails updating either durations or work.

This is useful when determining the impact of schedule variances on downstream work.

Some of you with architecture background may find Article 2 interesting because it is from the owner’s perspective. It is a pretty thorough description of the owner’s schedule review process, just like Article 2. Article 5 and 6 are about the timeline issue with getting baseline schedule approved by the owner at the beginning of the project.

However, very little in this article is about “automating”. Article 3 is a short blurp on schedule review from a neutral stand point.

Sometimes you can actually follow an individual’s work.

Or better yet, you could become one of those individuals/leaders if you are willing to share what you have learned in your profession.

the necessity of project schedule updating monitoring statusing-34the necessity of project schedule updating monitoring statusing-29the necessity of project schedule updating monitoring statusing-5

I am having a hard time deciding which would be the required reading.

One thought on “the necessity of project schedule updating monitoring statusing”